Brief
Nike Court covers approximately 60,000 m² of a logistics campus of around 120,000 m².
The building contains highly automated logistics infrastructure, including a large automated warehouse. ELC installed the cable routes, the cabling, the connections and the lighting.
Scope
Challenges and approach
Automated warehouse
Automation requires stable supplies and many connection points.
Cable routes coordinated with the automation installer.
Working at height
Lighting and cable trays hang high in the hall.
Cable trays pre-assembled on the ground and lifted in long lengths.
Large floor area
60,000 m² under one roof.
Work zones per section, with a dedicated crew per zone.
Timeline
Preparation
Cable routes aligned with the automation.
Cable routes
Cable trays installed per section.
Cabling and lighting
Supplies, connections and lighting.
Handover
Inspection and handover.
More projects
All projectsAartsen
Electrical installations and approx. 1,800 solar panels for a 21,500 m² distribution centre.
Project pageBakker Logistiek
Renovation of the electrical installations: new distribution boards, cable routes and cabling.
Project pageKeus Overduin Seijster Veste
Approx. 2,600 solar panels for a project in the Utrecht / Zeist region.
Project pageA similar project in preparation? Then we prefer to look at the drawings together.
Start a project request