EDUCATION AND RESEARCH · LEUVEN

KU Leuven, renovation projects

Renovation works in three KU Leuven buildings, from a historic library to the mechanical engineering buildings.

Divisions on this siteElectricalFiber & data networks
Client
KU Leuven
Our role
Electrical renovation, data and detection
Location
Leuven
Sites
3 buildings

Brief

ELC carried out electrical renovation works in several KU Leuven buildings, each time combining data cables, fire detection and electrical renovation.

The Zwarte Zusterhof Library is part of Leuven’s historic university fabric and was modernised while retaining its heritage character. In Mechanical Engineering, new lighting and technical infrastructure for an engineering environment were added.

Scope

Erasmus and teaching buildingsData cables, fire detection and electrical renovation.
Zwarte Zusterhof LibraryData cables, fire detection and electrical renovation in a historic complex.
Mechanical EngineeringLighting, data cables, fire detection and electrical renovation.
KU Leuven, renovation projects - site image
IN FIGURES
3
buildings

Challenges and approach

01

Heritage

CHALLENGE

Zwarte Zusterhof is a historic complex.

APPROACH

Cable routes concealed in existing shafts and ceilings, without visible interventions in the heritage parts.

02

Academic year keeps running

CHALLENGE

Teaching and research continue as usual.

APPROACH

Noisy works during holidays, changeovers per wing.

03

Engineering environment

CHALLENGE

Mechanical engineering has labs and workshops with their own equipment.

APPROACH

Supplies per lab in consultation with the research groups.

KU Leuven, renovation projects - detail
KU Leuven, renovation projects - works in progress
KU Leuven, renovation projects - handover

Timeline

PHASE 01

Survey per building

Existing installations and heritage constraints mapped.

PHASE 02

Detection and data

Fire detection and data cables per building.

PHASE 03

Electrical renovation

Boards, cabling and lighting renewed.

PHASE 04

Handover

Inspection and documentation per building.