Brief
An investment of more than €600 million, on a site of approximately 23 hectares, with two glass furnaces and more than 500 direct jobs.
The site contains heavy electrical infrastructure, with medium-voltage and low-voltage installations and industrial utilities. ELC is carrying out general electrical works, external lighting, welding and industrial electrical infrastructure.
Scope
Challenges and approach
Greenfield at large scale
A completely new 23-hectare site, with many parties on site at once.
Work zones per building, aligned with the main contractor’s programme.
Heavy industry
An environment with high temperatures and heavy utilities.
Cables and materials selected for temperature and mechanical load.
External areas
Roads and car parks around the entire factory.
External lighting per zone, controlled by daylight.
Timeline
Preparation
Work zones and cable routes worked out per building.
Infrastructure
Cable routes, cabling and welding.
External areas
External lighting of roads and car parks.
Start-up
Measurements and handover per zone.
More projects
All projectsJanssen Pharmaceutica
Electrical infrastructure and industrial works on the campus in Beerse, including the LION lab building.
Project pageUmicore
Industrial electrical installations, instrumentation and machine connections on a refining site.
Project pagePhilips
General electrical installations and infrastructure for Philips sites in Antwerp.
Project pageA similar project in preparation? Then we prefer to look at the drawings together.
Start a project request